Duncan – Roper Mountain Road – Garlington Road Widening

The Roper Mountain Road/Garlington Road Widening Project is located in Greenville, SC. Despite the continuous traffic and utility nightmare, Sloan crews and subcontractors have made great strides on this project. Construction started in May 2015 and crews have not looked back since. Sloan Construction crews have laid roughly 2,000 Lf of storm drain in midst of heavy traffic and constant utility conflicts. All the clearing and grubbing for this job is completed; and five moving items have been moved free of the right of way. In recent weeks over 2000 Lf of curb and gutter have also been poured on the job. In the coming months, Sloan will prepare to begin paving parts of Roper Mountain Road and installing signal poles at the intersection of Roper Mtn. Road and Garlington Rd. With continuing efforts from multiple parties associated with this project, Sloan Construction plans to complete this project by September 2016, and hand over a great product to the SCDOT.

Project Gallery

Print Friendly, PDF & Email